Abstract: In a case involving a building that was damaged due to shifting ground, the judge denied all defense motions and permitted the case to be argued to the jury on the theories of negligent design, negligent construction and breach of contract against all of the defendants. The lesson? If parties to a construction contract can’t resolve their differences via negotiation or arbitration, those differences may be decided by lay jurors who may have no background in construction.